A current transformer and a gateway hub. Two products, one system, and a client buying the pieces from four different places.
The thing that almost decided this schedule was not a mold. It was one enclosure revision — cheap where it happened, expensive everywhere else.
That is the whole argument of this article: the same design change has a different price depending on when you make it.
Four Vendors, One Schedule
This was never a quality problem. It was a sequencing problem.
When the board comes from one shop, the enclosure from another, the firmware from a third and the prototypes from a fourth, every supplier is individually reasonable and every supplier is late in a different week. The client becomes the integration layer — the only party who can see all four schedules, and the only party with no authority to change any of them.
The failure mode is not a bad part. It is a decision nobody can make, because the information needed to make it sits in four different inboxes.
For a two-product system the inbox count doubles. The CT and the hub share a radio link, a power architecture and a user’s expectation that they behave as one object. Change the hub’s enclosure and the CT may not care — but move the hub’s board outline and the enclosure, the antenna keep-out and the firmware’s I/O map all move together, in three different companies, in three different weeks.
The Interfaces Freeze in One Direction
There is a fixed order to this work:
ID → structure → board outline → firmware I/O → tooling
Each step consumes the previous step’s output. Whoever moves last pays for everyone.
A late ID change is not an ID change. It is a structural change, a board change and a firmware change, wearing an ID change’s clothes. That is why the cheapest possible moment to be indecisive about a design is before any of it is committed — and why the most expensive moment is the week after the tool is ordered.
What a Prototype Can Decide, and What It Cannot
A 3D printed enclosure is a decision tool, not a product. Its value is entirely in which questions it answers before you spend money on the ones that are still open.
It can settle:
- Whether the two boards physically fit, and where they interfere
- Whether the ports, buttons and indicators land where a hand expects them
- Whether the assembly order is possible without a fixture nobody has designed yet
- Whether the form factor reads as the product you are trying to sell
It cannot tell you:
- What the part will actually measure after shrinkage, and whether that passes tolerance
- Whether the wall will sink at the boss, or warp on the long side
- What the texture will look like on a production tool, and whether it will drag on ejection
- What the assembly force will be when the same clip is molded in PC rather than printed resin
- Whether the tool can be cut at all, with the draft and the shut-offs the design implies
The gap between those two lists is where projects get hurt. Teams frequently print a housing, confirm it snaps together by hand, and conclude the design is validated. What they validated was geometry. Structure and process were never in the test.
On this programme the printed parts did the job they are good at: they let two products be assembled and held before any tool existed, and they made one enclosure revision a matter of days rather than a matter of steel.
The Second ID Version
Midway through the development phase, the client’s own product thinking moved and the hub needed a new ID — not a cosmetic tweak, but a different enclosure form.
That change was absorbed by printing one more set. One extra prototype, one extra review, and the revised direction went into the small-batch build instead of the rejected one.
Had the same decision landed four weeks later, it would have been a tool modification: re-cut steel, new first articles, a re-run of dimensional approval, and a schedule slip measured in weeks. Had the old tooling already produced a batch, the sunk cost would have been paid twice — once for the parts, once for the correction.
The window for changing a design closes at the first cut of steel. Everything before that moment is negotiation. Everything after it is invoicing.
This is why we would rather spend a week printing a fifth set than a month defending a decision nobody likes. The prototype is not there to prove the design is right. It is there to make it cheap to find out it is not.
Why Two Batches, Not One
The build phase was split on purpose, and the split is worth understanding because it is not the usual “samples, then production”.
First delivery — three CT units and two hub units, plus the revised-ID prototype. Enough to put a working system in front of a customer, a test rig and a firmware team simultaneously. Not enough to hide a problem behind statistics.
Second delivery — twenty CT units and three hubs. Enough to run a validation programme rather than a demonstration: multiple sites, multiple conditions, and a firmware team that can afford to break a unit.
The reason for two steps is that these two batches answer different questions. The first answers does this work. The second answers does it keep working when we are not watching. Compressing them into one order would have saved a shipment and cost the client a month of finding out.
Firmware came last, deliberately. Delivering it before the hardware was assembled would have meant validating code against a device that did not exist yet. The board, the enclosure and the code converged on the same week, and only then could the project close.
What Was Actually Delivered
The programme ran from a deposit in October to a closed project in March — under six months from design review to functional prototypes in a client’s hands.
2024-10-09 Deposit received, development phase opened
2025-01-22 3 CT + 2 hub delivered, plus 1 hub in the revised ID enclosure
2025-03-20 Final payment; 20 CT + 3 hub shipped
2025-03-27 Firmware delivered; project closed
Scope of that span: ID and structural review on both products, PCB manufacturing documentation for both boards, firmware delivery coordinated with the client’s software team, printed enclosures for fit and assembly trials, and small-batch assembly and test of every unit shipped.
Twenty-three units is not a production order. It is enough to prove a product, staff a pilot, and decide whether to spend on tooling — which is exactly what a development phase is for.
What We Would Do Differently
Two things, honestly.
Freeze the ID earlier. The second version was absorbed cheaply because it arrived during printing. It would have been cheaper still if the first review had surfaced it — the design questions that produced it were visible in the first model, and we did not push hard enough on them at that stage.
Print the assembly, not just the housing. The first prototype round validated the enclosure as an object. Printing the mating parts alongside it would have surfaced the assembly order question a round earlier.
Neither of these is a process failure. Both are the normal cost of developing a product with a client who is still deciding what the product is — which is most clients, and the reason the sequence above exists at all.
If You Are About to Order Tooling
Three questions worth answering before the purchase order, because all three get expensive afterwards:
- Has every part of this design been held in a hand, in the order it will be assembled? Not viewed in CAD. Held.
- Which decisions are still open, and which of them touch the tool? Anything touching the tool is a schedule decision, not a design preference.
- Who owns the interface between the board and the enclosure? If the answer is “the board house” and “the molder”, nobody does.
If the honest answer to the first is no, the tool can wait a fortnight. It usually should.
What to Send, and What Comes Back
Send us: the ID or 3D model, the board files or outline, the target market and certification requirement, the batch size you need to validate with, and the date you intend to commit to tooling.
You get back: a manufacturability review on both the enclosure and the board interface, a printed prototype plan with the questions it will answer, a two-phase build proposal with what each phase proves, and a tooling timeline that starts from your decision date, not ours.
If the design is not ready to be cut into steel, we will say so — and the printed part that proves it costs far less than the tool that discovers it.