A French manufacturer of mechanical assemblies sent drawings for two parts — a bottom pivot and a vane — and asked for a price.
We quoted it. They revised the drawings and asked again. We quoted that too. Then nothing, for a while. When they came back, the request had changed shape: samples first, and a conversation about how the mold tooling cost would be carried.
That sequence — quote, revise, requote, pause, return — is the ordinary life of a custom moulding project. It is also where most of the money is decided, and almost none of it is decided in the piece price.
A Quote Is Attached to a Revision, Not a Part
Every quotation carries four assumptions whether or not they are written down: a drawing revision, a material, a tolerance set, and a volume. Change one and the number changes, because the number was never a property of the part. It was a property of that combination.
Procurement literature makes the same point from the other side: an RfQ is only comparable across suppliers when the specifications are detailed enough that everyone is bidding on the same thing. The moment one bidder is quoting revision B and another is quoting revision A, the comparison stops meaning anything, however similar the numbers look.
The part number survives all of it. The price does not.
What Mold Tooling Cost Is Actually Attached To
When a drawing comes back, the first question is not “how much more”. It is “which of the three is this”.
Marking and cosmetic notes. A laser mark, a date-code position, a texture reference, a colour call-out. None of these touch steel. They may touch process — a texture change needs a different grain etch, a colour change needs a different masterbatch lot — but the cavity is untouched.
Tolerance tightening. Same geometry, tighter band. The steel stays; the process window moves. A dimension that was comfortable at ±0.15 becomes a capability study at ±0.05, and the answer may be a different gate position or a slower fill rather than a new tool.
Geometry. Wall thickness, rib height, boss depth, draft, an undercut, a parting line, a gate location. Every one of these is a steel decision, and each is expensive in a different way.
Most of the cost lives in the third category, and most of the third category arrives looking small.
The Small Revision Is the Expensive One
A wall that goes from one thickness to another reads as a two-line change. In the tool it is a different fill, a different cooling pattern, and possibly a different ejection plan.
A thinner wall freezes earlier. The gate sized to fill the original section may now short-shot before the far corner packs, and the fix is a gate change — steel. A thicker wall stays molten longer, packs differently, and can pull a sink into the face opposite. A rib added for stiffness adds a weld line on its far side, and a weld line on a cosmetic surface is a visible defect that polishing does not remove. A boss that gets deeper can need a lifter or a slide, which is not a tweak; it is a second tool.
None of this is an argument against revising. It is the argument for reading each revision against the tool rather than against the previous drawing — which is what a diff review is for.
The Silence Between Quote Two and the Order
The gap after a second quotation is normal, and it is rarely about price. Three things usually explain it: the project is being re-budgeted internally, the same drawing is out for parallel quotes, or the launch date moved and nobody has told the supplier yet.
A quotation has a validity window for a reason that is not pressure tactics. Machining hours, steel and heat treatment are bought when the work is scheduled. A price held for six months is a price that assumes the workshop’s costs did not move for six months.
The useful response to a pause is not to chase it. It is to keep the assumptions written down, so that when the project restarts the conversation begins from a known revision instead of a memory.
Who Carries the Tool
When this project came back, the client wanted to discuss the tooling cost. That conversation about mold tooling cost has exactly two honest structures.
Paid up front. The customer pays for the tool, owns it, and can move it. The piece price carries parts only. If the programme is cancelled, the loss is bounded and it is the customer’s.
Amortised into the piece price. The tool is recovered across the order. This is attractive when capital is tight and dangerous when volume is a forecast: the supplier is financing the customer’s forecast. If the forecast is wrong, either the supplier absorbs the tool or the piece price carries a correction later — and a correction later always reads as a price increase.
Both structures are the same money. They are not the same risk. Which one is right depends on how firm the volume is, not on which one puts the smaller number on page one.
Two Parts, One Decision
The pivot and the vane are separate parts and one mechanism: the vane locates in the pivot, and the assembly is only correct if both are correct. That changes the programme in ways that are easy to miss at quotation.
The DFM has to cover the pair, because a gate position that suits the vane’s own dimensions can be wrong for the face it presents to the pivot. The samples have to arrive together, because a fit cannot be checked against a part still in the tool. And the approval has to be one event, because two approvals on two dates produce two versions of the truth.
We wrote about this on a four-mould programme — why the sample date is the only date that matters — and this project is the two-part version of it.
What Was Actually Run
A French mechanical-equipment manufacturer needed a black moulded bottom pivot and a vane, precise enough to fit an existing assembly. The work went: quotation against the original drawings; re-quotation after the client’s revision; confirmation of the tooling arrangement and the sample requirement; DFM on the revised drawings, including gate position and draft angle; both moulds built; trial; samples; approval; production order.
The detail worth keeping is not the sequence. It is that the re-quotation happened before the DFM, and the DFM happened before the steel. Swap any two of those three and a commercial conversation becomes a repair job.
Closing
A quotation is a snapshot of a decision, and drawings keep moving. The projects that go well are not the ones where the drawing never changed. They are the ones where each change was priced, read against the tool, and answered before the next cut.